High Point Drive (Hwy 25 to Parkhill Dr)

Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Redevelopment

Budget

Finished at $2,371,903 against an original approval of $3,220,463$848,560 under.

Council later reduced the budget by $821,401 to $2,399,062 (-26%).

99% of the current budget has been drawn.

Originally approved by Council$3,220,463
Change since approval-$821,401
Current budget$2,399,062
Spent to date$2,371,903
Against the original approval$848,560 under

Source: capital financial statement, document 15221, page 10. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (24 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$116,527$136,868$48,08735%
2023-03-27$116,527$150,425$91,96461%
2023-05-08$3,336,990$3,370,888$119,9444%
2023-06-19$3,336,990$3,370,888$131,9014%
2023-09-11$3,220,463$3,220,463$116,5614%
2023-09-11$116,527$141,369$141,369100%
2023-09-11$3,220,463$3,220,463$116,5614%
2023-09-11$116,527$141,369$141,369100%
2023-10-23$3,220,463$3,220,463$965,21530%
2023-12-18$3,220,463$3,220,463$2,094,74665%
2024-04-15$3,220,463$3,220,463$2,140,90966%
2024-05-13$3,220,463$3,220,463$2,124,09066%
2024-06-03$3,220,463$3,220,463$2,144,91667%
2024-09-09$3,220,463$3,220,463$2,360,08073%
2024-10-07$3,220,463$3,220,463$2,366,98073%
2024-12-09$3,220,463$3,220,463$2,367,42574%
2025-04-28$3,220,463$2,543,987$2,369,92893%
2025-05-26$3,220,463$2,543,987$2,369,92893%
2025-06-23$3,220,463$2,543,987$2,369,92893%
2025-09-08$3,220,463$2,399,062$2,371,07399%
2025-12-08$3,220,463$2,399,062$2,371,56299%
2026-04-13$3,220,463$2,399,062$2,371,56299%
2026-05-11$3,220,463$2,399,062$2,371,67599%
2026-06-22$3,220,463$2,399,062$2,371,90399%

The figure Council approved changed by $3,103,936 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.