Bronte Street (Main St to Steeles Ave)

Completed Pending Warranty / Community Services / Infrastructure Management / Urban Roads Redevelopment

Budget

Spent $28,107,699 against an original approval of $22,279,835$5,827,864 over (+26%).

Council later raised the budget by $9,178,287 to $31,458,122 (+41%).

89% of the current budget has been drawn.

Originally approved by Council$22,279,835
Change since approval$9,178,287
Current budget$31,458,122
Spent to date$28,107,699
Against the original approval$5,827,864 over

Source: capital financial statement, document 15221, page 10. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (26 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$33,434,927$35,770,607$22,052,35862%
2023-03-27$33,434,927$35,870,607$26,179,92573%
2023-05-08$33,434,927$35,870,609$26,266,56573%
2023-06-19$33,434,927$35,870,609$26,769,38375%
2023-09-11$33,434,927$36,032,956$28,194,66878%
2023-09-11$33,434,927$36,032,956$28,194,66878%
2023-10-23$33,434,927$36,032,956$29,427,94882%
2023-12-18$33,434,927$36,032,956$29,930,93283%
2024-04-15$33,434,927$36,032,956$32,092,72089%
2024-05-13$33,434,927$36,032,956$31,681,73288%
2024-06-03$33,434,927$36,032,956$32,229,35589%
2024-09-09$11,155,092$4,574,834$4,171,48291%
2024-10-07$11,155,092$4,574,834$4,174,32091%
2024-12-09$11,155,092$4,574,834$4,174,51991%
2025-04-28$11,155,092$4,574,834$4,175,90891%
2025-05-26$11,155,092$4,574,834$4,570,744100%
2025-05-26$22,279,835$31,458,122$28,081,13889%
2025-06-23$11,155,092$4,574,834$4,571,197100%
2025-06-23$22,279,835$31,458,122$28,081,13889%
2025-09-08$11,155,092$4,574,834$4,571,197100%
2025-09-08$22,279,835$31,458,122$28,081,13889%
2025-12-08$11,155,092$4,574,834$4,577,961100%
2025-12-08$22,279,835$31,458,122$28,076,09489%
2026-04-13$22,279,835$31,458,122$28,105,64489%
2026-05-11$22,279,835$31,458,122$28,107,69989%
2026-06-22$22,279,835$31,458,122$28,107,69989%

The figure Council approved changed by $11,155,092 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.