The Milton Record

6th Line (Hwy 401 to Britannia Rd)

Community Services

Budget

$522,604 spent so far of the $959,703 originally approved (48% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $124,062 to $1,083,765 (+13%).

48% of the current budget has been drawn.

Originally approved by Council$959,703
Change since approval$124,062
Current budget$1,083,765
Spent to date$522,604
Against the original approval$437,099 not yet spent — still in progress

Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (13 statements)
Statement dateApprovedCurrent budgetSpent%
2024-05-13$959,703$959,703$11,0471%
2024-06-03$959,703$959,703$14,8822%
2024-09-09$959,703$1,023,765$67,2787%
2024-10-07$959,703$1,023,765$71,9177%
2024-12-09$959,703$1,023,765$75,3907%
2025-04-28$959,703$1,023,765$145,28414%
2025-05-26$959,703$1,023,765$181,57618%
2025-06-23$959,703$1,023,765$186,05918%
2025-09-08$959,703$1,023,765$226,24622%
2025-12-08$959,703$1,023,765$444,98843%
2026-04-13$959,703$1,083,765$506,60847%
2026-05-11$959,703$1,083,765$519,72048%
2026-06-22$959,703$1,083,765$522,60448%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.