Completed Pending Warranty / Community Services / Parks / Parks Redevelopment
Finished at $513,813 against an original approval of $517,958 — $4,145 under.
Council later reduced the budget by $2,385 to $515,573 (-0%).
100% of the current budget has been drawn.
| Originally approved by Council | $517,958 |
|---|---|
| Change since approval | -$2,385 |
| Current budget | $515,573 |
| Spent to date | $513,813 |
| Against the original approval | $4,145 under |
Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Completed Pending Warranty / Community Services / Parks / Parks Redevelopment.