Melanie Park Redevelopment

Completed Pending Warranty / Community Services / Parks / Parks Redevelopment

Budget

$672,324 spent so far of the $816,166 originally approved (94% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $102,863 to $713,303 (-13%).

94% of the current budget has been drawn.

Originally approved by Council$816,166
Change since approval-$102,863
Current budget$713,303
Spent to date$672,324
Against the original approval$143,842 not yet spent — still in progress

Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.