Budget

$102,303 spent so far of the $2,799,985 originally approved (4% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

4% of the current budget has been drawn.

Originally approved by Council$2,799,985
Change since approval—
Current budget$2,799,985
Spent to date$102,303
Against the original approval$2,697,682 not yet spent — still in progress

Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (3 statements)

Statement dateApprovedCurrent budgetSpent%
2026-05-11$2,799,985$2,799,985—0%
2026-06-22$2,799,985$2,799,985—0%
2026-09-14$2,799,985$2,799,985$102,3034%

The figure Council approved has not changed across these statements. Spending against it rose by $102,303 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Streetlighting

Filed by the Town under Community Services / Active / Infrastructure Management / Streetlighting.

Elsewhere on this site