Community Services / Active / Infrastructure Management / Streetlighting
$6,301 spent so far of the $216,369 originally approved (3% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
3% of the current budget has been drawn.
| Originally approved by Council | $216,369 |
|---|---|
| Change since approval | — |
| Current budget | $216,369 |
| Spent to date | $6,301 |
| Against the original approval | $210,068 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 11. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $200,204 | $200,204 | $81,473 | 41% |
| 2025-05-26 | $208,325 | $208,325 | $19,201 | 9% |
| 2025-06-23 | $208,325 | $208,325 | $19,201 | 9% |
| 2025-09-08 | $208,325 | $208,325 | $35,339 | 17% |
| 2025-12-08 | $208,325 | $208,325 | $35,339 | 17% |
| 2026-04-13 | $141,104 | $141,104 | $4,109 | 3% |
| 2026-05-11 | $216,369 | $216,369 | $4,109 | 2% |
| 2026-06-22 | $216,369 | $216,369 | $4,109 | 2% |
| 2026-09-14 | $216,369 | $216,369 | $6,301 | 3% |
The figure Council approved changed by $16,165 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Community Services / Active / Infrastructure Management / Streetlighting.