Boyne Pedestrian Bridge - Minor Crossing

Development Services / Active / Development Engineering / Active Transportation - Growth

Budget

$263,314 spent so far of the $393,363 originally approved (67% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

67% of the current budget has been drawn.

Originally approved by Council$393,363
Change since approval—
Current budget$393,363
Spent to date$263,314
Against the original approval$130,049 not yet spent — still in progress

Source: capital financial statement, document 16410, page 14. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (3 statements)

Statement dateApprovedCurrent budgetSpent%
2026-05-11$393,363$393,363$263,31467%
2026-06-22$393,363$393,363$263,31467%
2026-09-14$393,363$393,363$263,31467%

The figure Council approved has not changed across these statements.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Active Transportation - Growth

Filed by the Town under Development Services / Active / Development Engineering / Active Transportation - Growth.

Elsewhere on this site