Development Services / Active / Development Engineering / Active Transportation - Growth
$570,372 spent so far of the $1,160,841 originally approved (39% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $290,088 to $1,450,929 (+25%).
39% of the current budget has been drawn.
| Originally approved by Council | $1,160,841 |
|---|---|
| Change since approval | $290,088 |
| Current budget | $1,450,929 |
| Spent to date | $570,372 |
| Against the original approval | $590,469 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 14. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-05-11 | $1,160,841 | $1,182,066 | $565,544 | 48% |
| 2026-06-22 | $1,160,841 | $1,450,929 | $567,707 | 39% |
| 2026-09-14 | $1,160,841 | $1,450,929 | $570,372 | 39% |
The figure Council approved has not changed across these statements. Spending against it rose by $4,828 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Development Services / Active / Development Engineering / Active Transportation - Growth.