Zero Radius Mowers

Fleet Equipment - Growth Related

Budget

$0 spent so far of the $159,738 originally approved (0% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $22,093 to $137,645 (-14%).

0% of the current budget has been drawn.

Originally approved by Council$159,738
Change since approval-$22,093
Current budget$137,645
Spent to date
Against the original approval$159,738 not yet spent — still in progress

Source: capital financial statement, document 15221, page 8. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (14 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$49,584$53,953$1,4443%
2023-03-27$49,584$53,953$1,4443%
2023-05-08$49,584$53,953$1,4443%
2023-06-19$49,584$53,953$1,4443%
2023-09-11$49,584$53,953$1,4443%
2023-09-11$49,584$53,953$1,4443%
2023-10-23$49,584$53,953$1,4443%
2023-12-18$49,584$53,953$53,952100%
2024-04-15$49,584$53,952$1000%
2024-05-13$87,897$87,8970%
2024-06-03$87,897$87,897$72,64683%
2024-09-09$87,897$75,206$75,206100%
2026-05-11$159,738$159,7380%
2026-06-22$159,738$137,6450%

The figure Council approved changed by $110,154 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Fleet Equipment - Growth Related

Filed by the Town under Fleet Equipment - Growth Related.

Elsewhere on this site