Transit Study Implementation

Corporate Services / Active / Transit / Transit Studies and Other

Budget

$147,539 spent so far of the $328,282 originally approved (45% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

45% of the current budget has been drawn.

Originally approved by Council$328,282
Change since approval
Current budget$328,282
Spent to date$147,539
Against the original approval$180,743 not yet spent — still in progress

Source: capital financial statement, document 15221, page 4. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (13 statements)
Statement dateApprovedCurrent budgetSpent%
2024-05-13$328,282$328,2820%
2024-06-03$328,282$328,2820%
2024-09-09$328,282$328,282$9,5623%
2024-10-07$328,282$328,282$9,5623%
2024-12-09$328,282$328,282$9,5623%
2025-04-28$328,282$328,282$57,67018%
2025-05-26$328,282$328,282$57,67018%
2025-06-23$328,282$328,282$57,67018%
2025-09-08$328,282$328,282$57,67018%
2025-12-08$328,282$328,282$57,67018%
2026-04-13$328,282$328,282$147,53945%
2026-05-11$328,282$328,282$147,53945%
2026-06-22$328,282$328,282$147,53945%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.