Transit Bus Stop-Retrofit

Corporate Services / Active / Transit / Transit Studies and Other

Budget

$0 spent so far of the $19,570 originally approved (0% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

0% of the current budget has been drawn.

Originally approved by Council$19,570
Change since approval
Current budget$19,570
Spent to date
Against the original approval$19,570 not yet spent — still in progress

Source: capital financial statement, document 15221, page 4. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (13 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$73,600$73,600$9,26813%
2023-03-27$73,600$73,600$23,92133%
2023-05-08$73,600$73,600$23,92133%
2023-06-19$73,600$73,600$78,400107%
2023-09-11$73,600$78,400$1000%
2023-09-11$73,600$78,400$1000%
2025-05-26$181,280$181,2800%
2025-06-23$181,280$181,2800%
2025-09-08$181,280$181,280$5,2803%
2025-12-08$181,280$181,280$138,85677%
2026-04-13$181,280$224,797$1000%
2026-05-11$19,570$19,5700%
2026-06-22$19,570$19,5700%

The figure Council approved changed by $54,030 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Transit Studies and Other

Filed by the Town under Corporate Services / Active / Transit / Transit Studies and Other.

Elsewhere on this site