Health and Safety Audit/Implementation

Corporate Services / Active / Corporate Services / Human Resources

Budget

$13,552 spent so far of the $32,321 originally approved (7% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later raised the budget by $161,031 to $193,352 (+498%).

7% of the current budget has been drawn.

Originally approved by Council$32,321
Change since approval$161,031
Current budget$193,352
Spent to date$13,552
Against the original approval$18,769 not yet spent — still in progress

Source: capital financial statement, document 15221, page 3. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (23 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$128,750$128,750$3,7503%
2023-03-27$128,750$128,750$3,7503%
2023-05-08$161,071$161,071$3,7502%
2023-06-19$161,071$161,071$12,6828%
2023-09-11$161,071$161,071$17,91011%
2023-09-11$161,071$161,071$17,91011%
2023-10-23$161,071$161,071$20,65713%
2023-12-18$161,071$161,071$23,39615%
2024-04-15$161,071$161,071$23,39615%
2024-05-13$209,553$209,553$23,39611%
2024-06-03$209,553$209,553$23,39611%
2024-09-09$209,553$209,553$24,80812%
2024-10-07$209,553$209,553$24,80812%
2024-12-09$209,553$209,553$24,80812%
2025-04-28$209,553$209,553$24,80812%
2025-05-26$241,874$241,874$24,80810%
2025-06-23$241,874$241,874$24,80810%
2025-09-08$241,874$241,874$29,20112%
2025-12-08$241,874$241,874$49,46320%
2026-04-13$32,321$193,352$13,5527%
2026-04-13$209,553$48,522$1000%
2026-05-11$32,321$193,352$13,5527%
2026-06-22$32,321$193,352$13,5527%

The figure Council approved changed by $96,429 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Human Resources

Filed by the Town under Corporate Services / Active / Corporate Services / Human Resources.

Elsewhere on this site