Community Park - External to Boyne

Community Services / Active / Community Services / Parks / Parks Growth

Budget

Spent $435,038 against an original approval of $310,101$124,937 over (+40%).

Council later raised the budget by $203,821 to $513,922 (+66%).

85% of the current budget has been drawn.

Originally approved by Council$310,101
Change since approval$203,821
Current budget$513,922
Spent to date$435,038
Against the original approval$124,937 over

Source: capital financial statement, document 15221, page 6. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (22 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$310,101$513,922$269,36752%
2023-03-27$310,101$513,922$340,33866%
2023-05-08$310,101$513,922$388,88476%
2023-06-19$310,101$513,922$392,69776%
2023-09-11$310,101$513,922$406,34079%
2023-09-11$310,101$513,922$406,34079%
2023-10-23$310,101$513,922$411,46280%
2023-12-18$310,101$513,922$417,25881%
2024-04-15$310,101$513,922$421,29582%
2024-05-13$310,101$513,922$421,29582%
2024-06-03$310,101$513,922$421,29582%
2024-09-09$310,101$513,922$421,29582%
2024-10-07$310,101$513,922$421,34082%
2024-12-09$310,101$513,922$421,64982%
2025-04-28$310,101$513,922$426,07183%
2025-05-26$310,101$513,922$426,11683%
2025-06-23$310,101$513,922$426,11683%
2025-09-08$310,101$513,922$426,17783%
2025-12-08$310,101$513,922$435,02885%
2026-04-13$310,101$513,922$435,03885%
2026-05-11$310,101$513,922$435,03885%
2026-06-22$310,101$513,922$435,03885%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.