Bridges/Culverts Redevelopment
$30,378 spent so far of the $870,316 originally approved (3% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
3% of the current budget has been drawn.
| Originally approved by Council | $870,316 |
|---|---|
| Change since approval | — |
| Current budget | $870,316 |
| Spent to date | $30,378 |
| Against the original approval | $839,938 not yet spent — still in progress |
Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2025-05-26 | $870,316 | $870,316 | — | 0% |
| 2025-06-23 | $870,316 | $870,316 | — | 0% |
| 2025-09-08 | $870,316 | $870,316 | $25,349 | 3% |
| 2025-12-08 | $870,316 | $870,316 | $25,349 | 3% |
| 2026-04-13 | $870,316 | $870,316 | $25,349 | 3% |
| 2026-05-11 | $870,316 | $870,316 | $30,235 | 3% |
| 2026-06-22 | $870,316 | $870,316 | $30,378 | 3% |
The figure Council approved has not changed across these statements.
Filed by the Town under Bridges/Culverts Redevelopment.