Campbellville Road Culvert (Structure No. 202)

Bridges/Culverts Redevelopment

Budget

$30,378 spent so far of the $870,316 originally approved (3% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

3% of the current budget has been drawn.

Originally approved by Council$870,316
Change since approval
Current budget$870,316
Spent to date$30,378
Against the original approval$839,938 not yet spent — still in progress

Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (7 statements)
Statement dateApprovedCurrent budgetSpent%
2025-05-26$870,316$870,3160%
2025-06-23$870,316$870,3160%
2025-09-08$870,316$870,316$25,3493%
2025-12-08$870,316$870,316$25,3493%
2026-04-13$870,316$870,316$25,3493%
2026-05-11$870,316$870,316$30,2353%
2026-06-22$870,316$870,316$30,3783%

The figure Council approved has not changed across these statements.

On the works map
Campbellville Road3% drawn
C390112
culvertoriginal $870,316

Other lines under Bridges/Culverts Redevelopment

Filed by the Town under Bridges/Culverts Redevelopment.