Bridges/Culverts Redevelopment
$405,246 spent so far of the $623,548 originally approved (65% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
65% of the current budget has been drawn.
| Originally approved by Council | $623,548 |
|---|---|
| Change since approval | — |
| Current budget | $623,548 |
| Spent to date | $405,246 |
| Against the original approval | $218,302 not yet spent — still in progress |
Source: capital financial statement, document 15221, page 9. These figures were parsed from that document and reconciled against the totals it states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2022-12-19 | $124,803 | $124,803 | $3,635 | 3% |
| 2023-03-27 | $124,803 | $124,803 | $3,635 | 3% |
| 2023-05-08 | $124,803 | $124,803 | $3,635 | 3% |
| 2023-06-19 | $124,803 | $124,803 | $3,635 | 3% |
| 2023-09-11 | $124,803 | $124,803 | $3,635 | 3% |
| 2023-09-11 | $124,803 | $124,803 | $3,635 | 3% |
| 2023-10-23 | $124,803 | $124,803 | $3,635 | 3% |
| 2023-12-18 | $124,803 | $124,803 | $5,996 | 5% |
| 2024-04-15 | $124,803 | $124,803 | $8,542 | 7% |
| 2024-05-13 | $124,803 | $124,803 | $13,096 | 10% |
| 2024-06-03 | $124,803 | $124,803 | $13,096 | 10% |
| 2024-09-09 | $124,803 | $124,803 | $15,706 | 13% |
| 2024-10-07 | $124,803 | $124,803 | $20,460 | 16% |
| 2024-12-09 | $124,803 | $124,803 | $22,541 | 18% |
| 2025-04-28 | $124,803 | $124,803 | $26,862 | 22% |
| 2025-05-26 | $623,548 | $623,548 | $33,328 | 5% |
| 2025-06-23 | $623,548 | $623,548 | $33,328 | 5% |
| 2025-09-08 | $623,548 | $623,548 | $48,058 | 8% |
| 2025-12-08 | $623,548 | $623,548 | $139,850 | 22% |
| 2026-04-13 | $623,548 | $623,548 | $402,559 | 65% |
| 2026-05-11 | $623,548 | $623,548 | $404,991 | 65% |
| 2026-06-22 | $623,548 | $623,548 | $405,246 | 65% |
The figure Council approved changed by $498,745 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Bridges/Culverts Redevelopment.