Development Services / Active / Development Engineering / Storm Water Management Growth
$5,337 spent so far of the $183,250 originally approved (2% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $126,467 to $309,717 (+69%).
2% of the current budget has been drawn.
| Originally approved by Council | $183,250 |
|---|---|
| Change since approval | $126,467 |
| Current budget | $309,717 |
| Spent to date | $5,337 |
| Against the original approval | $177,913 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 14. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2022-12-19 | $222,720 | $227,926 | $87,662 | 38% |
| 2023-05-08 | $343,448 | $348,654 | $113,539 | 33% |
| 2024-12-09 | $464,176 | $479,382 | $281,697 | 59% |
| 2025-05-26 | $474,919 | $494,919 | $187,914 | 38% |
| 2025-06-23 | $474,919 | $494,919 | $188,098 | 38% |
| 2025-09-08 | $474,919 | $494,919 | $196,118 | 40% |
| 2025-12-08 | $474,919 | $494,919 | $216,980 | 44% |
| 2026-04-13 | $474,919 | $494,919 | $234,582 | 47% |
| 2026-05-11 | $537,441 | $557,441 | $240,207 | 43% |
| 2026-06-22 | $537,441 | $557,441 | $240,630 | 43% |
| 2026-09-14 | $183,250 | $309,717 | $5,337 | 2% |
The figure Council approved changed by $39,470 between 2022-12-19 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.