Development Services / Active / Development Engineering / Storm Water Management Growth
$6,954 spent so far of the $195,280 originally approved (2% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $103,401 to $298,681 (+53%).
2% of the current budget has been drawn.
| Originally approved by Council | $195,280 |
|---|---|
| Change since approval | $103,401 |
| Current budget | $298,681 |
| Spent to date | $6,954 |
| Against the original approval | $188,326 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 14. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $133,614 | $133,614 | $4,592 | 3% |
| 2025-05-26 | $267,228 | $267,228 | $6,081 | 2% |
| 2025-06-23 | $267,228 | $267,228 | $8,281 | 3% |
| 2025-09-08 | $267,228 | $267,228 | $13,685 | 5% |
| 2025-12-08 | $267,228 | $267,228 | $30,961 | 12% |
| 2026-04-13 | $267,228 | $267,228 | $31,246 | 12% |
| 2026-05-11 | $328,894 | $328,894 | $33,672 | 10% |
| 2026-06-22 | $328,894 | $328,894 | $34,214 | 10% |
| 2026-09-14 | $195,280 | $298,681 | $6,954 | 2% |
The figure Council approved changed by $61,666 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $2,362 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.