Pending Closure / Community Services / Infastructure Management / Storm Water Management Rehabilitation
$100 spent so far of the $798,554 originally approved (0% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later reduced the budget by $141,735 to $656,819 (-18%).
0% of the current budget has been drawn.
| Originally approved by Council | $798,554 |
|---|---|
| Change since approval | -$141,735 |
| Current budget | $656,819 |
| Spent to date | $100 |
| Against the original approval | $798,454 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 13. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-04-13 | $670,401 | $1,056,414 | $1,056,414 | 100% |
| 2026-09-14 | $798,554 | $656,819 | $100 | 0% |
The figure Council approved changed by $128,153 between 2026-04-13 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Pending Closure / Community Services / Infastructure Management / Storm Water Management Rehabilitation.