Pending Closure / Community Services / Infastructure Management / Rural Roads Redevelopment
Spent $1,370,023 against an original approval of $778,242 — $591,781 over (+76%).
Council later raised the budget by $591,781 to $1,370,023 (+76%).
0% of the current budget has been drawn.
| Originally approved by Council | $778,242 |
|---|---|
| Change since approval | — |
| Current budget | $1,370,023 |
| Spent to date | $1,370,023 |
| Against the original approval | $591,781 over |
Source: capital financial statement, document 16410, page 13. This figure was read from that page, and the total for its section adds up to what the document states.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Pending Closure / Community Services / Infastructure Management / Rural Roads Redevelopment.