Community Services / Active / Facilities / Facilities Redevelopment
$63,704 spent so far of the $295,282 originally approved (24% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later reduced the budget by $31,100 to $264,182 (-11%).
24% of the current budget has been drawn.
| Originally approved by Council | $295,282 |
|---|---|
| Change since approval | -$31,100 |
| Current budget | $264,182 |
| Spent to date | $63,704 |
| Against the original approval | $231,578 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 8. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-05-11 | $295,282 | $264,182 | $11,823 | 4% |
| 2026-06-22 | $295,282 | $264,182 | $17,807 | 7% |
| 2026-09-14 | $295,282 | $264,182 | $63,704 | 24% |
The figure Council approved has not changed across these statements. Spending against it rose by $51,881 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Community Services / Active / Facilities / Facilities Redevelopment.