The Milton Record

Memorial Arena Facility Improvements

Community Services / Active / Facilities / Facilities Redevelopment

Budget

$63,704 spent so far of the $295,282 originally approved (24% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $31,100 to $264,182 (-11%).

24% of the current budget has been drawn.

Originally approved by Council$295,282
Change since approval-$31,100
Current budget$264,182
Spent to date$63,704
Against the original approval$231,578 not yet spent — still in progress

Source: capital financial statement, document 16410, page 8. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (3 statements)

Statement dateApprovedCurrent budgetSpent%
2026-05-11$295,282$264,182$11,8234%
2026-06-22$295,282$264,182$17,8077%
2026-09-14$295,282$264,182$63,70424%

The figure Council approved has not changed across these statements. Spending against it rose by $51,881 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.