The Milton Record

FirstOntario Arts Centre Milton Facility Improvements

Community Services / Active / Facilities / Facilities Redevelopment

Budget

$682,891 spent so far of the $2,549,927 originally approved (28% of the current budget drawn). Still in progress, so this is neither over nor under.

Council later reduced the budget by $85,450 to $2,464,477 (-3%).

28% of the current budget has been drawn.

Originally approved by Council$2,549,927
Change since approval-$85,450
Current budget$2,464,477
Spent to date$682,891
Against the original approval$1,867,036 not yet spent — still in progress

Source: capital financial statement, document 16410, page 8. This figure was read from that page, and the total for its section adds up to what the document states.

How this budget changed over time (8 statements)

Statement dateApprovedCurrent budgetSpent%
2024-12-09$795,612$755,112$458,88361%
2025-05-26$1,254,357$1,213,857$512,78142%
2025-06-23$1,254,357$1,213,857$514,29342%
2025-09-08$1,254,357$1,168,907$533,04046%
2025-12-08$1,254,357$1,168,907$559,99848%
2026-05-11$2,549,927$2,464,477$611,40125%
2026-06-22$2,549,927$2,464,477$641,30526%
2026-09-14$2,549,927$2,464,477$682,89128%

The figure Council approved changed by $1,754,315 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $224,008 over the same period.

On the works map

No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.

Other lines under Facilities Redevelopment

Filed by the Town under Community Services / Active / Facilities / Facilities Redevelopment.