Executive Services / Pending Closure / Executive Services / Finance
Spent $7,884,067 against an original approval of $5,127,400 — $2,756,667 over (+54%).
Council later raised the budget by $2,756,667 to $7,884,067 (+54%).
100% of the current budget has been drawn.
| Originally approved by Council | $5,127,400 |
|---|---|
| Change since approval | $2,756,667 |
| Current budget | $7,884,067 |
| Spent to date | $7,884,067 |
| Against the original approval | $2,756,667 over |
Source: capital financial statement, document 16410, page 2. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2025-04-28 | $5,644,000 | $5,642,523 | $5,642,523 | 100% |
| 2026-09-14 | $5,127,400 | $7,884,067 | $7,884,067 | 100% |
The figure Council approved changed by $516,600 between 2025-04-28 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $2,241,544 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Executive Services / Pending Closure / Executive Services / Finance.