Corporate Services / Active / Corporate Services / Fire / Fire - Replacement
$13,309 spent so far of the $17,510 originally approved (76% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
76% of the current budget has been drawn.
| Originally approved by Council | $17,510 |
|---|---|
| Change since approval | — |
| Current budget | $17,510 |
| Spent to date | $13,309 |
| Against the original approval | $4,201 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 5. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $41,200 | $41,200 | $28,926 | 70% |
| 2026-05-11 | $17,510 | $17,510 | $9,173 | 52% |
| 2026-06-22 | $17,510 | $17,510 | $12,799 | 73% |
| 2026-09-14 | $17,510 | $17,510 | $13,309 | 76% |
The figure Council approved changed by $23,690 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Active / Corporate Services / Fire / Fire - Replacement.