11 days until Milton votes. Monday 26 October 2026. Everyone on the ballot, what each has filed, and what they say in their own words — see the ballot.
Corporate Services / Active / Corporate Services / Fire / Fire - Replacement
$3,362 spent so far of the $115,412 originally approved (3% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
3% of the current budget has been drawn.
| Originally approved by Council | $115,412 |
|---|---|
| Change since approval | — |
| Current budget | $115,412 |
| Spent to date | $3,362 |
| Against the original approval | $112,050 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 5. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $15,450 | $15,450 | $11,526 | 75% |
| 2025-05-26 | $56,650 | $56,650 | $11,526 | 20% |
| 2025-06-23 | $56,650 | $56,650 | $11,526 | 20% |
| 2025-09-08 | $56,650 | $56,650 | $12,726 | 22% |
| 2025-12-08 | $56,650 | $56,650 | $12,726 | 22% |
| 2026-04-13 | $56,650 | $56,650 | $15,632 | 28% |
| 2026-05-11 | $130,862 | $130,862 | $15,632 | 12% |
| 2026-06-22 | $130,862 | $130,862 | $15,632 | 12% |
| 2026-09-14 | $115,412 | $115,412 | $3,362 | 3% |
The figure Council approved changed by $99,962 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Active / Corporate Services / Fire / Fire - Replacement.