Community Services / Active / Infrastructure Management / Bridges/Culverts Redevelopment
$1,758,235 spent so far of the $2,411,839 originally approved (82% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later reduced the budget by $259,282 to $2,152,557 (-11%).
82% of the current budget has been drawn.
| Originally approved by Council | $2,411,839 |
|---|---|
| Change since approval | -$259,282 |
| Current budget | $2,152,557 |
| Spent to date | $1,758,235 |
| Against the original approval | $653,604 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 10. This figure was read from that page, and is the Town’s published number. On spent to date, the 7 lines this site placed under that section add to $3,546,855 against $3,546,853 stated in the document, a difference of $2. A difference that small across figures printed to the dollar is what rounding looks like, so the total is not treated as verified, and the difference is stated rather than smoothed away. Document 16410, page 10.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $240,908 | $289,212 | $91,990 | 32% |
| 2025-05-26 | $2,411,839 | $2,460,143 | $165,516 | 7% |
| 2025-06-23 | $2,411,839 | $2,152,557 | $187,205 | 9% |
| 2025-09-08 | $2,411,839 | $2,152,557 | $274,805 | 13% |
| 2025-12-08 | $2,411,839 | $2,152,557 | $1,503,079 | 70% |
| 2026-04-13 | $2,411,839 | $2,152,557 | $1,739,182 | 81% |
| 2026-05-11 | $2,411,839 | $2,152,557 | $1,741,922 | 81% |
| 2026-06-22 | $2,411,839 | $2,152,557 | $1,741,922 | 81% |
| 2026-09-14 | $2,411,839 | $2,152,557 | $1,758,235 | 82% |
The figure Council approved changed by $2,170,931 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $1,666,245 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Community Services / Active / Infrastructure Management / Bridges/Culverts Redevelopment.