Corporate Services / Active / Corporate Services / Fire / Fire - Replacement
Spent $18,009 against an original approval of $15,450 — $2,559 over (+17%).
Council later raised the budget by $20,000 to $35,450 (+129%).
51% of the current budget has been drawn.
| Originally approved by Council | $15,450 |
|---|---|
| Change since approval | $20,000 |
| Current budget | $35,450 |
| Spent to date | $18,009 |
| Against the original approval | $2,559 over |
Source: capital financial statement, document 16410, page 5. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $21,548 | $21,548 | $9,168 | 43% |
| 2025-05-26 | $15,450 | $15,450 | — | 0% |
| 2025-06-23 | $15,450 | $15,450 | — | 0% |
| 2025-09-08 | $15,450 | $15,450 | $450 | 3% |
| 2025-12-08 | $15,450 | $15,450 | $11,259 | 73% |
| 2026-05-11 | $15,450 | $15,450 | — | 0% |
| 2026-06-22 | $15,450 | $15,450 | $17,559 | 114% |
| 2026-09-14 | $15,450 | $35,450 | $18,009 | 51% |
The figure Council approved changed by $6,098 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $8,841 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Active / Corporate Services / Fire / Fire - Replacement.