Development Services / Active / Planning and Development / Planning
$14,103 spent so far of the $474,393 originally approved (3% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
3% of the current budget has been drawn.
| Originally approved by Council | $474,393 |
|---|---|
| Change since approval | — |
| Current budget | $474,393 |
| Spent to date | $14,103 |
| Against the original approval | $460,290 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 14. This figure was read from that page, and is the Town’s published number. On spent to date, the 15 lines this site placed under that section add to $13,247,444 against $13,247,442 stated in the document, a difference of $2. A difference that small across figures printed to the dollar is what rounding looks like, so the total is not treated as verified, and the difference is stated rather than smoothed away. Document 16410, page 14.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2026-05-11 | $474,393 | $474,393 | $286 | 0% |
| 2026-06-22 | $474,393 | $474,393 | $286 | 0% |
| 2026-09-14 | $474,393 | $474,393 | $14,103 | 3% |
The figure Council approved has not changed across these statements. Spending against it rose by $13,817 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Development Services / Active / Planning and Development / Planning.