Capital works · local road · Proposed
$1,828,868 spent so far of the $3,885,865 originally approved (40% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $737,387 to $4,623,252 (+19%).
40% of the current budget has been drawn.
| Originally approved by Council | $3,885,865 |
|---|---|
| Change since approval | $737,387 |
| Current budget | $4,623,252 |
| Spent to date | $1,828,868 |
| Against the original approval | $2,056,997 not yet spent — still in progress |
Source: capital financial statement, document 15221, page 8. Matched to this project by exact-core at 97% confidence, and reconciled against the totals stated in that document.
| Anticipated start | 2025-01-01 |
|---|---|
| Status | PROPOSED |
| Project manager | MARK NORMAN |
| Contact | 905-878-7252 ext 2277 |
| Responsibility | Town of Milton |