C330146 · collector · Proposed
$4,963,875 spent so far of the $21,286,763 originally approved (16% of the current budget drawn). Still in progress, so this is neither over nor under.
Council later raised the budget by $9,932,141 to $31,218,904 (+47%).
16% of the current budget has been drawn.
| Originally approved by Council | $21,286,763 |
|---|---|
| Change since approval | $9,932,141 |
| Current budget | $31,218,904 |
| Spent to date | $4,963,875 |
| Against the original approval | $16,322,888 not yet spent — still in progress |
Source: capital financial statement, document 15221, page 8. Matched to this project by exact-core at 97% confidence, and reconciled against the totals stated in that document.
| Anticipated start | 2025-07-15 |
|---|---|
| Completion | 2027-07-31 |
| Duration | 2025 - 2027 Construction |
| Status | PROPOSED |
| Project manager | David Muraca |
| Contact | 905-878-7252 ext 2398 |
| Responsibility | Town of Milton |