Town Hall Construction/Expansion

Community Services / Facilities / Facilties Growth

Budget

$19,975 spent so far of the $604,975 originally approved (3% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

3% of the current budget has been drawn.

Originally approved by Council$604,975
Change since approval
Current budget$604,975
Spent to date$19,975
Against the original approval$585,000 not yet spent — still in progress

Source: capital financial statement, document 15221, page 7. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (22 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$604,975$604,975$19,9753%
2023-03-27$604,975$604,975$19,9753%
2023-05-08$604,975$604,975$19,9753%
2023-06-19$604,975$604,975$19,9753%
2023-09-11$604,975$604,975$19,9753%
2023-09-11$604,975$604,975$19,9753%
2023-10-23$604,975$604,975$19,9753%
2023-12-18$604,975$604,975$19,9753%
2024-04-15$604,975$604,975$19,9753%
2024-05-13$604,975$604,975$19,9753%
2024-06-03$604,975$604,975$19,9753%
2024-09-09$604,975$604,975$19,9753%
2024-10-07$604,975$604,975$19,9753%
2024-12-09$604,975$604,975$19,9753%
2025-04-28$604,975$604,975$19,9753%
2025-05-26$604,975$604,975$19,9753%
2025-06-23$604,975$604,975$19,9753%
2025-09-08$604,975$604,975$19,9753%
2025-12-08$604,975$604,975$19,9753%
2026-04-13$604,975$604,975$19,9753%
2026-05-11$604,975$604,975$19,9753%
2026-06-22$604,975$604,975$19,9753%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.