Surface Treatment Program

Roadway Maintenance

Budget

$775,994 spent so far of the $2,123,691 originally approved (37% of the current budget drawn). Still in progress, so this is neither over nor under.

Council has not changed this budget since approving it.

37% of the current budget has been drawn.

Originally approved by Council$2,123,691
Change since approval
Current budget$2,123,691
Spent to date$775,994
Against the original approval$1,347,697 not yet spent — still in progress

Source: capital financial statement, document 15221, page 8. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (25 statements)
Statement dateApprovedCurrent budgetSpent%
2022-12-19$1,905,802$1,905,802$1,467,34977%
2023-03-27$1,905,802$1,905,802$1,475,67577%
2023-05-08$3,065,836$3,065,836$1,475,67548%
2023-06-19$3,065,836$3,065,836$1,475,67548%
2023-09-11$3,065,836$3,065,836$1,522,28850%
2023-09-11$3,065,836$3,065,836$1,522,28850%
2023-10-23$3,065,836$3,065,836$2,454,92280%
2023-12-18$3,065,836$3,065,836$2,471,58581%
2024-04-15$2,127,535$2,127,535$1,569,96174%
2024-04-15$938,301$973,604$1000%
2024-05-13$3,152,616$3,152,616$1,571,57350%
2024-06-03$3,152,616$3,152,616$1,571,57350%
2024-09-09$3,152,616$3,152,616$1,606,97051%
2024-10-07$3,152,616$3,152,616$1,904,83060%
2024-12-09$3,152,616$3,152,616$2,762,78388%
2025-04-28$1,025,081$1,025,081$850,89483%
2025-04-28$2,127,535$2,095,5422095542%
2025-05-26$2,067,311$2,067,311$850,89441%
2025-06-23$2,067,311$2,067,311$850,89441%
2025-09-08$2,067,311$2,067,311$881,25043%
2025-12-08$2,067,311$2,067,311$1,267,31961%
2026-04-13$1,042,230$1,042,230$775,99474%
2026-04-13$1,025,081$1,039,283$1,039,283100%
2026-05-11$2,123,691$2,123,691$775,99437%
2026-06-22$2,123,691$2,123,691$775,99437%

The figure Council approved changed by $217,889 between 2022-12-19 and 2026-06-22. A project can be re-scoped or re-approved, and each statement records where it stood that month.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.