Subdivision Agreement Review

Development Services / Active / Studies and Other / Studies and Other

Budget

Spent $57,227 against an original approval of $30,900$26,327 over (+85%).

Council later raised the budget by $30,000 to $60,900 (+97%).

94% of the current budget has been drawn.

Originally approved by Council$30,900
Change since approval$30,000
Current budget$60,900
Spent to date$57,227
Against the original approval$26,327 over

Source: capital financial statement, document 15221, page 12. These figures were parsed from that document and reconciled against the totals it states.

How this budget changed over time (7 statements)
Statement dateApprovedCurrent budgetSpent%
2025-05-26$30,900$30,900$9,50631%
2025-06-23$30,900$30,900$16,10552%
2025-09-08$30,900$30,900$26,43986%
2025-12-08$30,900$30,900$40,692132%
2026-04-13$30,900$60,900$54,53490%
2026-05-11$30,900$60,900$57,22794%
2026-06-22$30,900$60,900$57,22794%

The figure Council approved has not changed across these statements.

On the works map
No mapped capital works project is matched to this budget line.

The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.