Corporate Services / Active / Corporate Services / Fire / Fire - Growth
$114,709 spent so far of the $161,277 originally approved (71% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
71% of the current budget has been drawn.
| Originally approved by Council | $161,277 |
|---|---|
| Change since approval | — |
| Current budget | $161,277 |
| Spent to date | $114,709 |
| Against the original approval | $46,568 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 5. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $74,160 | $74,160 | $19,512 | 26% |
| 2025-05-26 | $190,653 | $190,653 | $64,057 | 34% |
| 2025-06-23 | $190,653 | $190,653 | $121,353 | 64% |
| 2025-09-08 | $190,653 | $190,653 | $144,876 | 76% |
| 2025-12-08 | $190,653 | $190,653 | $155,145 | 81% |
| 2026-04-13 | $190,653 | $190,653 | $155,145 | 81% |
| 2026-05-11 | $235,437 | $235,437 | $161,019 | 68% |
| 2026-06-22 | $235,437 | $235,437 | $186,774 | 79% |
| 2026-09-14 | $161,277 | $161,277 | $114,709 | 71% |
The figure Council approved changed by $87,117 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month. Spending against it rose by $95,197 over the same period.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Active / Corporate Services / Fire / Fire - Growth.