Corporate Services / Active / Corporate Services / Transit / Transit Fleet Growth
$51,906 spent so far of the $225,027 originally approved (23% of the current budget drawn). Still in progress, so this is neither over nor under.
Council has not changed this budget since approving it.
23% of the current budget has been drawn.
| Originally approved by Council | $225,027 |
|---|---|
| Change since approval | — |
| Current budget | $225,027 |
| Spent to date | $51,906 |
| Against the original approval | $173,121 not yet spent — still in progress |
Source: capital financial statement, document 16410, page 4. This figure was read from that page, and the total for its section adds up to what the document states.
| Statement date | Approved | Current budget | Spent | % |
|---|---|---|---|---|
| 2024-12-09 | $402,540 | $402,540 | $379,816 | 94% |
| 2025-05-26 | $225,027 | $225,027 | — | 0% |
| 2025-06-23 | $225,027 | $225,027 | — | 0% |
| 2025-09-08 | $225,027 | $225,027 | $6,554 | 3% |
| 2025-12-08 | $225,027 | $225,027 | $9,130 | 4% |
| 2026-04-13 | $225,027 | $225,027 | $9,130 | 4% |
| 2026-05-11 | $225,027 | $225,027 | $35,982 | 16% |
| 2026-06-22 | $225,027 | $225,027 | $51,906 | 23% |
| 2026-09-14 | $225,027 | $225,027 | $51,906 | 23% |
The figure Council approved changed by $177,513 between 2024-12-09 and 2026-09-14. A project can be re-scoped or re-approved, and each statement records where it stood that month.
The Town publishes its works map and its financial statements separately, with no shared identifier. Where a confident match cannot be made by name, none is asserted.
Filed by the Town under Corporate Services / Active / Corporate Services / Transit / Transit Fleet Growth.